I have a requirement to specify Due Date based on an SLA for a task. The Due Date on the task needs to taskCreateDateTime + SLA hours. I am not sure, how this can be achieved in the Activiti 7 Modeler.
You can create task listener and assign to task create event.
In Tasklistner you can set due date.
Hi @amod-gadre
Are you using APA? If so, I don't believe there are tasklisteners in APA - you would need to use a process variable.
HTH,
Ask for and offer help to other Alfresco Process Services and Activiti Users and members of the Alfresco team.
By using this site, you are agreeing to allow us to collect and use cookies as outlined in Alfresco’s Cookie Statement and Terms of Use (and you have a legitimate interest in Alfresco and our products, authorizing us to contact you in such methods). If you are not ok with these terms, please do not use this website.