Hello
With Activiti 5.10 change due date was possible with the following 2 lines
task.setDueDate(..)
ProcessEngines.getDefaultProcessEngine().getTaskService().save(task)
With Activiti 5.11 we have the following exception on the line 2 :
Caused by: org.activiti.engine.ActivitiOptimisticLockingException: TaskEntity[109811] was updated by another transaction concurrently

Any idea?

Merry Christmas