AnsweredAssumed Answered

Why is the field in the table due_date_ act_hi_taskinst are

Question asked by kolmogorov.dikma on Jan 28, 2013
Latest reply on Jan 28, 2013 by kolmogorov.dikma
Why is the field in the table due_date_ act_hi_taskinst not contain a date after the completion of the task?

1) Create a task in the field due_date_ act_ru_task contains date

Task task = taskService.newTask();
task.setName(taskEntity.getName());
task.setDescription(taskEntity.getDescription());
task.setPriority(taskEntity.getPriority());
task.setDueDate(taskEntity.getDueDate());
task.setOwner(taskEntity.getOwner());
task.setAssignee(taskEntity.getAssignee());
taskService.saveTask(task);
2) complete the task

taskService.complete(taskId);

Activiti version 5.11

Outcomes