Hi

If i have a deployment with a process (process1) containing a CallActivity starting another process (process2) then deploy a new version of these processes, what will the existing process instances of process1 start when reaching the CallActivity starting process2. The version from the old deployment, from which the process instance is started, or the new version?

The reason that I am asking is that we have this situation where we have added some new parameters to process2 and now all existing instances from the old version is failing when starting(and executing) process2 with the message that the new property does not exist.