AnsweredAssumed Answered

Finish all user tasks (when running in parallel)

Question asked by cljungblad on Oct 16, 2015
Latest reply on Oct 20, 2015 by martin.grofcik
Hi,

I have three User Tasks running in parallel

startEvent –>parallel gateway –> (Task1, Task2, Task3) –> parallel gateway –> endEvent

Now, when finishing any of (Task1, Task2 or Task3) I want to automatically cancel/complete the other two tasks as well, and finish the process. I've tried to use signals to end the other two tasks, but it does not work as expected. I was wondering what is the best approach to tackle this.

So my question is:
Is it possible to complete all user task, when one of the three user tasks are completed (using BPMN2.0 only)?

Thanks
Christopher

Outcomes