AnsweredAssumed Answered

Generated diagram does not show task names

Question asked by felipe1 on Aug 18, 2016
Latest reply on Aug 18, 2016 by felipe1
After upgrade from version 5.15 to version 5.21.0 diagrams generated for ongoing process instances are not showing task names. However, diagrams generated for process definitions continue showing task names:

Here is the generated diagram for process definitions:
[img]https://dl.dropboxusercontent.com/u/51893421/diagram-process-definition-has-task-names.png[/img]

This is the code used to generate the diagram above:
ProcessEngines.getDefaultProcessEngine().getRepositoryService().getResourceAsStream(processDefinitionEntity.getDeploymentId(), processDefinitionEntity.getDiagramResourceName());

Here is the generated diagram for ongoing process instances
[img]https://dl.dropboxusercontent.com/u/51893421/diagram-ongoing-process-instance-no-task-names.png[/img]

This is the code used to generate the diagram above:
ProcessEngines.getDefaultProcessEngine().getProcessEngineConfiguration().getProcessDiagramGenerator().generateDiagram(myBpmnModel, "png", myActitivies);

Is there a way to show task names on the second diagram as well?


Cheers!
Felipe.

Outcomes