Is it possible to configure timer boundary event with multi instance user task so that timer boundary event will be multi instance too.
For example, i have 3 assignees: use1, user2, user3 and I want to have individual timer for every assignee.
Does activiti engine allow such configuration?
Using activiti-5.19.0.1
Solved! Go to Solution.
Not directly on a multi instance user task. Use an embedded sub-process and keep the embedded subprocess multi instance to achieve a timer per task.
Not directly on a multi instance user task. Use an embedded sub-process and keep the embedded subprocess multi instance to achieve a timer per task.
Thank you very much! That's what I need.
Ask for and offer help to other Alfresco Process Services and Activiti Users and members of the Alfresco team.
By using this site, you are agreeing to allow us to collect and use cookies as outlined in Alfresco’s Cookie Statement and Terms of Use (and you have a legitimate interest in Alfresco and our products, authorizing us to contact you in such methods). If you are not ok with these terms, please do not use this website.